STATE AID PROJECTS LET BY CONTRACT DURING JANUARY, 2005

BOLIVAR COUNTY- BR-0609(2)B - 0.514 miles of BOX BRIDGES & APPROACHES on SHAW-KIMBALL LAKE-MOUND BAYOU ROAD. Let to EnDevCo., Inc. of Oxford, MS on Tuesday, January 18, 2005. Contract Amount $1,190,397.35 ($1,249,900.00)

CHICKASAW COUNTY- BR-0009(17)B - 0.185 miles of BRIDGES & APPROACHES on BUENA VISTA-BRINDLETOWN ROAD. Let to Dye Construction, Inc. of Tupelo, MS on Thursday, January 20, 2005. Contract Amount $181,338.50 ($190,400.00)

DESOTO COUNTY- DECD-0017(36)B - 0.833 miles of GRADE, DRAIN, BASE & SURFACE on AIRWAYS BOULEVARD. Let to Chancellor Brothers, LLC of Cordova, TN on December 21, 2004. Contract Amount $1,200,037.95 ($1,260,000.00)

HANCOCK COUNTY- DECD-1106(4)B - 2.800 miles of WIDENING & OVERLAY on LOWER BAY ROAD. Let to Huey Stockstill, Inc. of Jackson, MS on Tuesday, December 21, 2004. Contract Amount $1,157,993.65 ($1,215,900.00)

LEFLORE COUNTY- STP-0042(17)B - 4.397 miles of RESEAL on ROADS "A" - "C". Let to J. J. Ferguson Sand & Gravel, Inc. of Greenwood, MS on Monday, January 4, 2005. Contract Amount $283,852.38 ($298,000.00)

PONTOTOC COUNTY- SAP-58(58) - 2.224 miles of GRADE, DRAIN, BASE & SURFACE on REDLAND-SAREPTA ROAD (Co. Rd. No. 884). Let to TLSL, Inc. of Walnut, MS on Thursday, December 23, 2004. Contract Amount $663,545.40 ($696,700.00)

RANKIN COUNTY- SAP-61(81) - 0.218 miles of BRIDGE & APPROACHES on DANIEL-CONCORD CHURCH-CLARKSBURG ROAD. Let to Joe McGee Construction Co., Inc. of Lake, MS on Friday, January 14, 2005. Contract Amount $738,502.27 ($775,400.00)

SIMPSON COUNTY- SAP-64(61) - 0.306 miles of GRADE, DRAIN, BASE & SURFACE on AIRPORT ROAD. Let to James E. Clark Contractors, LLC of Soso, MS on Tuesday, December 21, 2004. Contract Amount $215,767.73 ($226,600.00)

WAYNE COUNTY- SAP-77(81) - 1.559 miles of BASE & SURFACING on THOMPSON CREEK CHURCH-WHISTLER ROAD. Let to Dunn Roadbuilders, LLC of Laurel, MS on Thursday, January 13, 2005. Contract Amount $132,520.53 ($139,100.00)

WINSTON COUNTY- SAP-80(1)M - 0.132 miles of MAINTENANCE (other than bridge) on POPLAR FLAT ROAD. Let to Joe McGee Construction Co., Inc. of Lake, MS on Monday, January 10, 2005. Contract Amount $94,382.95 ($99,100.00)



LSBP PROJECTS LET BY CONTRACT DURING JANUARY, 2005

LAWRENCE COUNTY- LSBP-39(11) - 0.093 miles of BOX BRIDGE & APPROACHES on REID-GIVENS ROAD. Let to Pace Brothers Enterprises, Inc. of Columbia, MS on Tuesday, January 18, 2005. Contract Amount $123,636.45 ($129,800.00)

LEAKE COUNTY- LSBP-40(9) - 0.170 miles of BRIDGE & APPROACHES on ROBINSON ROAD. Let to Mid-South Construction, Inc. of Columbia, MS on Wednesday, January 12, 2005. Contract Amount $240,426.75 ($252,400.00)

PERRY COUNTY- LSBP-56(6) - 0.109 miles of BRIDGE & APPROACHES on FLORIDA GAS ROAD. Let to Bush Construction Co., Inc. of Laurel, MS on Tuesday, January 25, 2005. Contract Amount $117,830.65 ($123,700.00)

PRENTISS COUNTY- LSBP-59(15) - 0.154 miles of PC BEAM BRIDGE & APPROACHES on COUNTY ROAD NO. 1151. Let to Prairie Construction, LLC of Tupelo, MS on Friday, January 14, 2005. Contract Amount $271,743.88 ($285,200.00)



STATE AID PROJECTS BY FORCE ACCOUNT
AND/OR COUNTY FORCES DURING JANUARY, 2005

MONROE COUNTY- SAP-48(10)M - 24.734 miles of OVERLAY on ROADS "A" - "H". Let to the Monroe County Board of Supervisors of Aberdeen, MS on January 31, 2005. Contract Amount $1,322,198.55 ($1,388,300.00)

MONROE COUNTY- SAP-48(16)S - 20.884 miles of RESEAL on ROADS "A" - "F". Let to the Monroe County Board of Supervisors of Aberdeen, MS on January 31, 2005. Contract Amount $521,322.95 ($547,400.00)