GEORGE COUNTY- SAP-20(6)M - 10.781 miles of OVERLAY on ROADS "A" - "C'. Let to Mobile Asphalt Company, LLC of Mobile, AL on Friday, February 11, 2005. Contract Amount $817,695.43 ($858,600.00)
GEORGE COUNTY- SAP-20(11)S - 22.344 miles of RESEAL on ROADS "A" - "G". Let to Mobile Asphalt Company, LLC of Mobile, AL on Friday, February 11, 2005. Contract Amount $627,878.86 ($659,300.00)
GRENADA COUNTY- LSRP-22(1) - 2.542 miles of GRADE, DRAIN, BASE & SURFACE on NEILA ROAD. Let to EnDevCo., Inc. of Oxford, MS on February 10, 2005. Contract Amount $710,839.43 ($746,400.00)
HANCOCK COUNTY- SAP-23(7)M - 10.405 miles of MAINTENANCE (other than bridge) on FENTON RD. and DUMMY LINE RD.. Let to Warren Paving, Inc. of Gulfport, MS on Wednesday, February 23, 2005. Contract Amount $1,565,668.94 ($1,644,000.00)
GEORGE COUNTY- LSBP-20(7) - 0.100 miles of BRIDGE & APPROACHES on TURNER ROAD. Let to Clark Brothers Construction, Inc. of Laurel, MS on Tuesday, February 22, 2005. Contract Amount $114,526.50 ($120,300.00)
GEORGE COUNTY- LSBP-20(8) - 0.156 miles of BRIDGE & APPROACHES on VARDAMAN GRAVES ROAD. Let to Jordan Crane Service, Inc. of Taylorsville, MS on Tuesday, February 22, 2005. Contract Amount $196,604.10 ($206,400.00)
PANOLA COUNTY- LSBP-54(8) - 0.472 miles of BOX BRIDGES, BOX CULVERT & APPROACHES on EDWARDS RD., LESLIE RD., COLD SPRINGS RD., RIVER RD.. Let to Talbot Brothers Contracting Co., Inc. of Nesbit, MS on Monday, Friday 14, 2005. Contract Amount $798,659.62 ($838,600.00)
SCOTT COUNTY- LSBP-62(9) - 0.128 miles of BOX BRIDGE & APPROACHES on SPRINGFIELD ROAD. Let to Joe McGee Construction Co., Inc. of Lake, MS on Monday, February 7, 2005. Contract Amount $160,687.45 ($168,700.00)
SUNFLOWER COUNTY- LSBP-67(8) - 0.222 miles of BRIDGES & APPROACHES on MARKHAM RD., SOUTH TAYLOR ROAD. Let to J. J. Ferguson Sand & Gravel, Inc. of Greenwood, MS on Monday, February 7, 2005. Contract Amount $359,482.78 ($377,500.00)
WINSTON COUNTY- LSBP-80(10) - 0.120 miles of BOX BRIDGES & APPROACHES on LOAKFOMA ROAD (SITES "A" & "B"). Let to Hall's Construction Co., Inc. of New Albany, MS on Friday, February 25, 2005. Contract Amount $164,722.28 ($173,000.00)
[ - None - ]