STATE AID PROJECTS LET BY CONTRACT DURING AUGUST, 2006

CARROLL COUNTY- BR-0764(5)B - 0.772 miles of BRIDGES, BOX BRIDGES & APPROACHES on TECO ROAD (CO. RD. NO. 73). Let to EnDevCo., Inc. of Oxford, MS on Tuesday, August 8, 2006. Contract Amount $1,314,299.97 ($1,380,000.00)

COAHOMA COUNTY- SAP-14(7)M - 2.856 miles of OVERLAY on NEW AFRICA ROAD. Let to Lehman-Roberts Company of Memphis, TN on Wednesday, August 16, 2006. Contract Amount $375,938.67 ($394,700.00)

MARSHALL COUNTY- SAP-47(6)M - 4.033 of OVERLAY on VICTORIA-CAYCE ROAD. Let to Standard Construction Co., Inc. of Germantown, TN on Monday, August 7, 2006. Contract Amount $439,257.87 ($461,200.00)

MONROE COUNTY- SAP-48(12)M - 0.037 miles of MAINTENANCE on OLD HWY 25 ROAD. Let to Ellis Construction Co., Inc. of Columbus, MS on Thursday, August 31, 2006. Contract Amount $137,776.77 ($144,700.00)

PRENTISS COUNTY- SAP-59(6)M - 0.033 miles of MAINTENANCE (OTHER THAN BRIDGE) on MARIETTA-ALCORN COUNTY ROAD. Let to Buddy Ayers Construction, Inc. of Corinth, MS on Thursday, August 10, 2006. Contract Amount $38,877.20 ($40,800.00)

TALLAHATCHIE COUNTY- BR-0068(10)B - 0.369 miles of BRIDGE & APPROACHES on SHELEY ROAD. Let to Harper Construction, Inc. of Paducah, KY on Friday, August 11, 2006. Contract Amount $1,819,479.83 ($1,910,500.00)

TISHOMINGO COUNTY- SAP-71(67) - 0.023 miles of BOX BRIDGE & APPROACHES on RED BUD RD.- ITAWAMBA COUNTY LINE ROAD. Let to Hall's Construction Co., Inc. of New Albany, MS on Friday, August 18, 2006. Contract Amount $194,150.69 ($203,900.00)

YALOBUSHA COUNTY- SAP-81(10)M - 0.018 miles of MAINTENANCE (other than bridge) on OLD HIGHWAY NO. 330 (CO. RD. NO. 211). Let to Townes Construction Co., Inc. of Grenada, MS on August 14, 2006. Contract Amount $36,792.50 ($38,600.00)



LSBP PROJECTS LET BY CONTRACT DURING AUGUST, 2006

CHICKASAW COUNTY- LSBP-09(9) - 0.133 miles of BRIDGE & APPROACHES on COUNTY ROAD NO. 43. Let to Dye Construction, Inc. of Shannon, MS on Tuesday, August 8, 2006. Contract Amount $208,216.35 ($218,600.00)

CLAY COUNTY- LSBP-13(9) - 0.113 miles of BOX BRIDGE & APPROACHES on STEELE ROAD. Let to Hall's Construction Co., Inc. of New Albany, MS on Thursday, August 17, 2006. Contract Amount $160,873.60 ($168,900.00)

SHARKEY COUNTY- LSBP-63(7) - 0.198 miles of BRIDGE & APPROACHES on MCINTYRE ROAD. Let to Buford Construction Co., Inc. of Vicksburg, MS on Monday, August 21, 2006. Contract Amount $343,975.82 ($361,200.00)

WALTHALL COUNTY- LSBP-74(9) - 0.152 miles of BRIDGE, BOX BRIDGE & APPROACHES on BROCKDALE, -ELLIS & BACOT ROAD. Let to Pace Brothers Enterprises, Inc. of Columbia, MS on Monday, August 7, 2006. Contract Amount $495,099.48 ($519,900.00)



STATE AID PROJECTS BY FORCE ACCOUNT
AND/OR COUNTY FORCES DURING AUGUST, 2006

[ - None - ]



STATE AID DEBRIS REMOVAL PROJECTS BY COUNTY FORCES
AUGUST, 2006

ADAMS COUNTY- ER-0001(21)B - COUNTYWIDE DEBRIS REMOVAL. Let to the ADAMS COUNTY BOARD OF SUPERVISORS of Natchez, MS on August 9, 2006. Project Amount $45,182.08

LAMAR COUNTY- ER-0037(23)B - COUNTYWIDE DEBRIS REMOVAL. Let to the LAMAR COUNTY BOARD OF SUPERVISORS of Purvis, MS on August 14, 2006. Project Amount $85,622.95

NEWTON COUNTY- ER-0051(26)B - COUNTYWIDE DEBRIS REMOVAL. Let to the NEWTON COUNTY BOARD OF SUPERVISORS of Decatur, MS on July 25, 2006. Project Amount $383,197.88

PERRY COUNTY- ER-0056(18)B - COUNTYWIDE DEBRIS REMOVAL. Let to the PERRY COUNTY BOARD OF SUPERVISORS of New Augusta, MS on June 12, 2006. Project Amount $1,030,996.63

SMITH COUNTY- ER-0065(24)B - COUNTYWIDE DEBRIS REMOVAL. Let to the SMITH COUNTY BOARD OF SUPERVISORS of Raleigh, MS on July 12, 2006. Project Amount $73,972.10

STONE COUNTY- ER-0066(24)B - COUNTYWIDE DEBRIS REMOVAL. Let to the STONE COUNTY BOARD OF SUPERVISORS of Wiggins, MS on August 9, 2006. Project Amount $1,304,729.49