STATE AID PROJECTS LET BY CONTRACT DURING JANUARY, 2007


CLAY COUNTY- SAP-13(38) - 0.037 miles of BOX BRIDGE & APPROACHES on TIBBEE ROAD. Let to Ausbern Construction Co., Inc. of Okolona, MS on Thursday, January 4, 2007. Contract Amount $120,083.70 ($126,100.00)


ITAWAMBA COUNTY- SAP-29(19)S - 17.465 miles of RESEAL on ROADS "A" - "G". Let to Bonds Company, Inc. of Burnsville, MS on Tuesday, January 16, 2007. Contract Amount $536,510.61 ($563,300.00)


PRENTISS COUNTY- SAP-59(68) - 0.349 miles of GRADE, DRAIN, BASE & SURFACE on NEW SITE-NEW HOPE ROAD (CR 3401). Let to Parsons Earthworks, Inc. of Iuka, MS on Wednesday, January 17, 2007. Contract Amount $150,775.51 ($158,300.00)


SMITH COUNTY- SAP-65(4)M - 0.030 miles of BRIDGE REPAIR on MIZE-GLISSON-RALEIGH ROAD. Let to Jordan Crane Service, Inc. of Taylorsville, MS on Monday, January 22, 2007. Contract Amount $138,930.00 ($145,900.00)



LSBP PROJECTS LET BY CONTRACT DURING JANUARY, 2007



CARROLL COUNTY- LSBP-08(19) - 0.075 miles of BOX CULVERT & APPROACHES on COUNTY ROAD NO. 65. Let to EnDevCo., Inc. of Oxford, MS on Monday, January 22, 2007. Contract Amount $169,411.01 ($177,900.00)


JEFFERSON COUNTY- LSBP-32(3) - 0.181 miles of BOX BRIDGES & APPROACHES on SITE "A"-RED BRICK CHURCH ROAD, "B"-TRULY LAKE ROAD. Let to Dozer, Inc. of Natchez, MS on Tuesday, January 23, 2007. Contract Amount $422,753.95 ($443,900.00)


UNION COUNTY- LSBP-73(13) - 0.075 miles of BRIDGE & APPROACHES on COUNTY ROAD NO. 61. Let to Phillips Contracting Co., Inc. of Columbus, MS on Monday, January 22, 2007. Contract Amount $274,658.90 ($288,400.00)



STATE AID PROJECTS BY FORCE ACCOUNT

AND/OR COUNTY FORCES DURING JANUARY, 2007

 

[ - None - ]




STATE AID DEBRIS REMOVAL PROJECTS BY COUNTY FORCES

DURING JANUARY, 2007






SCOTT COUNTY- ER-0062(16)B - COUNTYWIDE DEBRIS REMOVAL. Let to the SCOTT COUNTY BOARD OF SUPERVISORS of Forest, MS on January 26, 2007. Project Amount $84,112.00