This page created: 04/14/2025 07:07:47 AM
PANOLA COUNTY PROJECT STATUS
County......: PANOLA
Project No..: LSBP 54 11
Project Type: BRIDGE REPLACEMENT
Road Name...:
SMART ROAD (REVISED)
Termini.....:
COMMENCING AT THE SOUTHWEST CO
RNER OF SEC. 19, T6S, R5W; THE
NCE NORTH ALONG THE CENTERLINE
OF SMART ROAD FOR A DISTANCE
OF APPROXIMATELY 0.113 MILE.
Status......: Complete
Finaled:05/18/2007
Funds.......: $.0
Contractor..: Endevco, Inc.
|