                         PONTOTOC COUNTY PROJECT STATUS                         


County......: PONTOTOC
Project No..: SAP 58 4 M
Project Type: OVERLAY
Road Name...: 
A-ROAD NO.29 & B-ROAD NO. 886
Termini.....: 
A-BEGIN AT HWY 9 AT SW CORNER
SEC. 1, T9S, R3E, THENCE NE TO
END AT RD. 854  B-BEGIN AT RD
. 59 THENCE EAST TO END AT RD.
58
Status......: Complete
              Finaled:05/03/2004
Funds.......: $.0
Contractor..: BONDS COMPANY, INC.