This page created: 04/14/2025 07:07:47 AM

                         MARSHALL COUNTY PROJECT STATUS                         


County......: MARSHALL
Project No..: SAP 47 9 M
Project Type: BASE REPAIR, LEVELING, OVERLAY
Road Name...: 
SITE "A"  WATERFORD - BETHELEHEM RD.  SITE "B"  CORNERSVILLE -UNION CO
Termini.....: 
PREVIOUS PROJECTS SAP-47(10) A
ND SAP-47(51)    SITE"A" BEGIN
IN SECTION 13, T6S, R2W AND G
O TO THE INT. OF MS. HWY. 349
IN SECTION 8, T6S, R1W.  SITE
"B"  BEGIN AT THE INT. OF HWY
NO. 349 IN SEC. 24, T6S, R1W
Status......: Complete
              Finaled:06/04/2010
Funds.......: $.0
Contractor..: WG Construction, Inc