This page created: 04/14/2025 07:07:47 AM

                        SUNFLOWER COUNTY PROJECT STATUS                        


County......: SUNFLOWER
Project No..: LSBP 67 12
Project Type: REPLACE BRIDGES AND APPROACHES
Road Name...: 
SITE "A" STILLMAN ROAD SITE "B" STEED MIXON ROAD
Termini.....: 
STILLMAN ROAD SITE "A" SEC. 28
T20N R3W OVER DRAINAGE CANAL-
-SITE "B" STEED MIXON ROAD SEC
. 15 T20N R4W
Status......: Complete
              Finaled:09/29/2014
Funds.......: $.0
Contractor..: JJ Ferguson Sand & Gravel