This page created: 04/14/2025 07:07:47 AM

                          DESOTO COUNTY PROJECT STATUS                          


County......: DESOTO
Project No..: BR 0976 5 B
Project Type: BRIDGE REPLACEMENT
Road Name...: 
FOGG ROAD
Termini.....: 
BOP 1500' NORTH OF THE SW CORN
ER OF SEC 8 T3S R8W EOP 3900'
NORTH OF THE SW CORNER OF SEC
8 T3S R8W OVER HURRICANE CREEK
Status......: Complete
              Finaled:02/11/2020
Funds.......: $.0
Contractor..: Talbot Brothers Contracting