                           PIKE COUNTY PROJECT STATUS                           


County......: PIKE
Project No..: SAP 57 64
Project Type: MILL AND OVERLAY WITH HMA SOIL CEMENT BASE LINEAR GRADING EXISTING ALIGNMENT AND LIGHT LINEAR GRADIN
Road Name...: 
JOHN E LEWIS DRIVE
Termini.....: 
COMMENCE AT A POINT APPROX 250
0' W OF THE INTERSECTION OF JE
SSE HALL RD AND US HWY 51 NEAR
THE MIDDLE OF SEC 1 T2N R7E A
ND CONTINUE W AN NE ALONG NEW
ALIGNMENT FOR .8 MILES AND THE
N CONTINUE ON EXISTING JOHN E
LEWIS DR FOR DISTANCE .45 MILE
S TO AIRPO
Status......: Complete
              Finaled:06/20/2016
Funds.......: $.0
Contractor..: Dickerson & Bowen