This page created: 04/14/2025 07:07:47 AM

                        WASHINGTON COUNTY PROJECT STATUS                        


County......: WASHINGTON
Project No..: LSBP 76 15
Project Type: BRIDGE REPLACEMENT AND APPROACHES
Road Name...: 
SITE A- RUSSELL RD--SITE B-SLAGO DIARY RD--SITE C-SLAGO DIARY RD
Termini.....: 
SITE A-SEC 25 T19N--SITE B- SE
C 16 T17N R7W--SITE C-SEC18 T1
7N R7W
Status......: Complete
              Finaled:03/09/2015
Funds.......: $.0
Contractor..: Fordice Construction Co.