                          KEMPER COUNTY PROJECT STATUS                          


County......: KEMPER
Project No..: SAP 35 5 M
Project Type: ROAD A-REHAB 1-48' CONC PIPE W/SHOTCRETE ROAD B-REHAB 1-87'X63' & 2-92" X 65" STEEL PLATE ARCH PIPES
Road Name...: 
ROAD A-NEELYTOWN ROAD   B-HOPEWELL ROAD C-VARDAMAN ROAD
Termini.....: 
ROAD A PREVIOUS PROJECT SAP-35
(39) ROAD B-PREVIOUS PROJECT S
AP-35(30)  C-PREVIOUS PROJECT
SAP-35(10)
Status......: Complete
              Finaled:10/31/2014
Funds.......: $.0
Contractor..: Proshot Concrete, Inc.