This page created: 04/14/2025 07:07:47 AM

                         FRANKLIN COUNTY PROJECT STATUS                         


County......: FRANKLIN
Project No..: SAP 19 69
Project Type: RELOCATE EXISTING ROADWAY TO THE SOUTH TO AVOID ANY FURTHER DAMAGE
Road Name...: 
BERRYTOWN ROAD
Termini.....: 
BEGIN APPROX 1000 FEET WEST OF
AN EXISTING SLIDE FAILURE IN
S2 T5N R3E AND RUN TO APPROX 1
000' EAST OF THE EXISTING SLID
E FAILURE
Status......: Complete
              Finaled:01/03/2019
Funds.......: $.0
Contractor..: S & S Excavation LLC