                         WINSTON COUNTY PROJECT STATUS                         


County......: WINSTON
Project No..: BR 0080 31 B
Project Type: REPLACEMENT OF DEFICIENT BRIDGES WITH REQUIRED BRIDGE APPROACHES AND GUARDRAILS ON EXISTING PAVED RD
Road Name...: 
MILL CREEK (SITE A) FORMER PROJECT SAP-80(13) SHILOH (SITE B) SAP-80(1
Termini.....: 
AS REQUIRED FOR BRIDGE REPLACE
MENT AND APPROACHES S15-T15N-R
13E  (SITE A)- S21-T14N-R11E (
SITE B)
Status......: Complete
              Finaled:12/29/2015
Funds.......: $.0
Contractor..: NL Carson Const. Co. Inc.